On Nov. 18, 2025, Pittsburgh swapped a 1992 hub layout, and its train, for a $1.7 billion terminal built for people who start and end their trips here. Here is the before and after.
Photo: Antony-22, CC BY-SA 4.0 / Wikimedia Commons
Short answer
Pittsburgh International's $1.7 billion new terminal opened on Nov. 18, 2025. It replaced the 1992 landside terminal and the train with a building next to the gates, linked by the Skybridge. It added one 12-lane checkpoint, a new garage and lot, a faster bag system, and the Welcome Point, and the airport says no local tax dollars were used.
Verified
The new terminal, by the numbers
Interactive
Then vs now.
Drag the slider across the old and new layouts, then switch the table between before and now.
Drag to compare: old layout on the left, new on the right
Simplified diagrams, not to scale. The airside terminal and its four concourses are the same building as before; it was renovated rather than replaced.
| Item | Before Nov. 18, 2025 | Now |
|---|---|---|
| Getting to the gates | A people-mover train between the landside and airside terminals, about half a mile apart | The Skybridge, a walkway from the checkpoint to the Core and every gate, with lighting that changes through the day |
| Security | Main checkpoint with 7 lanes, plus an alternate checkpoint | One checkpoint with 12 lanes on the Departures level |
| Curb to airside | Train ride after security | About 50% less time from curb to airside, says the airport |
| Checked bags | About 8 miles of baggage belts | About 3 miles of belts; the airport expected delivery times to be cut in half |
| International arrivals | Tunnels to the trains, with domestic and international passengers kept apart | A dedicated corridor from customs to the Arrivals level; time to the curb cut by about two thirds |
| Baggage claim | In the old landside terminal | Eight carousels grouped by airline, nearly double the old claim area |
| Meeting a flight | Waiting in baggage claim | The Welcome Point, where every arriving passenger walks through |
| Parking | Short Term Garage plus Long Term, Extended and Economy lots | Terminal Garage (3,300 spaces), Terminal Lot and one Shuttle Lot; covered parking tripled |
| Outdoor space | None for passengers | Four planned terraces; the 36,000 sq ft UPMC Terrace opened in July 2026 |
| Built for | A US Airways hub (opened Oct. 1, 1992) where about 80% of travelers were connecting | Pittsburgh travelers: 98% of 2024 passengers started or ended their trip at PIT |
Checked October 19, 2026 against the airport's own site. PGH Nonstop is independent and is not the airport.
Three levels
How to get through it now
Departing
Top level
Drop off on the Departures curb, check in, clear the 12-lane checkpoint, pass the recompose area and walk the Skybridge to the Core and every gate.
Arriving
Middle level
Leave the gates through the automated exit lanes into the Welcome Point, then baggage claim. Friends pick you up right outside.
Ground
Bottom level
Rideshare, taxis, the 28X, hotel shuttles, and walkways to the Terminal Garage, Terminal Lot and rental car counters.
Design
Designed to feel like Pittsburgh
The architects, Gensler and HDR with luis vidal + architects, drew on the region's landscape: a rolling roofline, 38 tree-shaped steel columns, about 100,000 square feet of glass and "constellation" lighting with more than 4,000 lights. The terrazzo floors carry a leaf pattern by artist Clayton Merrell. About 16,000 tons of steel were fabricated locally, and the airport says more than 90% of labor and supplies were local.
It runs on the airport's own microgrid of natural gas and solar, which the airport describes as the first to fully power a major airport. The building is designed for 13 to 15 million passengers a year; PIT handled 9.85 million in 2025.
Timeline
From hub to home airport.
The airport opens as a US Airways hub, with a landside terminal and a train to the airside gates.
Christina Cassotis becomes CEO and refocuses PIT on Pittsburgh travelers rather than connections.
Groundbreaking on the Terminal Modernization Program.
A dedicated international baggage system opens on Concourse C's lower level.
Ribbon cutting for the new terminal.
Opening day. Just after 2 a.m. the team "went live", and the old landside terminal and train closed.
PIT becomes the first airport with Universal Design Certification from the University at Buffalo's IDEA Center. The rebuilt customs primary processing area opens.
Named to the Prix Versailles list of the World's Most Beautiful Airports.
The UPMC Terrace, the first of four planned terraces, opens to everyone.
LEED Gold for the terminal; Parksmart Gold for the Terminal Garage.
Air Transport World names PIT its 2027 Airport of the Year, the first U.S. airport to win twice.
A dedicated TSA PreCheck Touchless ID lane opens at the checkpoint.

First time through?
Find your gate before you land.
Our schematic shows the four concourses, which airlines the airport's map puts where, and the closest food to every gate.
Photo: Michael Righi, CC BY 2.0 / Wikimedia Commons
Questions
When did the new Pittsburgh airport terminal open?
How much did the new Pittsburgh airport terminal cost?
Is there still a train at Pittsburgh airport?
Where is the new Pittsburgh airport terminal?
Who designed the new PIT terminal?
What awards has the new terminal won?
More of the PIT guide
Sources
- Pittsburgh International Airport: The Transformed PIT
- Transformed PIT fact sheet, Aug. 21, 2025 (cost, size, groundbreaking, capacity, time savings)
- Blue Sky News: Transformed PIT Meets the Needs of Today and the Future, Nov. 24, 2025
- Blue Sky News: Know Before You Go, Nov. 17, 2025
- Blue Sky News: The Transformed PIT Has Arrived (opening day)
- Blue Sky News: A New Era: Pittsburgh Cuts the Ribbon (Oct. 11, 2025)
- Blue Sky News: Transformed PIT to Open Tuesday, Nov. 18 (design and economic facts)
- Blue Sky News: 100 Days In, March 2, 2026
- Blue Sky News: Prix Versailles, World's Most Beautiful Airports (June 2026; size, architects)
- Blue Sky News: ATW Names PIT Airport of the Year (Sept. 22, 2026)
- Blue Sky News: LEED Gold (Aug. 2026)
- Blue Sky News: UPMC Terrace opens (July 2026)
- The Transformed PIT: Skybridge, Baggage Claim, Terraces and Parking pages